[1]潘华炜,周 珺,丁 浩,等.地下连续墙施工过程中的变形控制研究[J].江苏水利,2017,(05):29-32.
 PAN Huawei,ZHOU Jun,DING Hao,et al.Study on deformation control of diaphragm wall during construction[J].JIANGSU WATER RESOURCES,2017,(05):29-32.
点击复制

地下连续墙施工过程中的变形控制研究()
分享到:

《江苏水利》[ISSN:1006-6977/CN:61-1281/TN]

卷:
期数:
2017年05期
页码:
29-32
栏目:
工程建设
出版日期:
2017-05-17

文章信息/Info

Title:
Study on deformation control of diaphragm wall during construction
文章编号:
1007-7839(2017)05-0029-04
作者:
潘华炜1周 珺2丁 浩1季建中3
1.江苏省苏水工程建设监理有限公司,江苏 扬州 225127;
2.江苏省水利勘测设计研究院有限公司,江苏 扬州 225127;
3.江苏省泰州引江河管理处,江苏 泰州 225321
Author(s):
PAN Huawei1ZHOU Jun2DING Hao1JI Jianzhong3
1.Jiangsu Province Sushui Engineering Construction Supervision Co.,Ltd,Yangzhou 225127,Jiangsu;
2.Jiangsu Provincial Water Conservancy Survey and Design Institute Co.,Ltd,Yangzhou 225127,Jiangsu;
3.Taizhou Linking Rive Management Division of Jiangsu Province,Taizhou 225321,Jiangsu
关键词:
地下连续墙施工变形控制
Keywords:
diaphragm wallconstructiondeformation control
分类号:
TV523
文献标志码:
B
摘要:
地下连续墙作为建设深基坑工程和地下构筑物的一项新技术,在水利建筑工程中越来越广泛应用。地下连续墙施工方法就是预先进行成槽开挖,形成一定长度的槽段,在槽段内放入预制好的钢筋笼,并浇筑混凝土形成墙段。实际上,地下连续墙成槽施工也是一系列的开挖和土体扰动过程,必然会产生一定的土体变形与位移。施工中极有可能发生槽段外土体变形过大,甚至引起地面塌陷,当建筑物或管线距槽段较近时,则可能会造成周边管线断裂、建筑物倾斜等严重的不良后果,本文基于引江河二线船闸地下连续墙施工过程进行了研究,不但为本工程的施工提供了指导,提高了地下连续墙的成型质量,并为以后类似工程施工提供借鉴。
Abstract:
As a new technology of the construction of deep foundation pit engineering and underground structure,diaphragm wall is more and more widely used in hydraulic engineering.The construction method of underground continuous wall is to dig into the trench in advance to form a groove with a certain length,and the prefabricated steel bar cage is inserted into the groove section,and the concrete wall is formed by pouring concrete.As a matter of fact,the construction of underground continuous wall is a series of excavation and soil disturbance process,which will produce certain deformation and displacement.The construction is likely soil that the deformation is too large,and even causes the ground collapse.When the building or pipeline from the slot section is close,it may cause adverse consequences around the pipeline fracture,building tilt serious,the rivers and the second ship lock underground continuous wall construction process based on the research,not only provides guidance for the construction of the project,improve the forming quality of underground continuous wall,but also provides reference for future similar project construction.

参考文献/References:

[1]丁勇春 .软土地区深基坑施工引起的变形及控制研究[D] .上海:上海交通大学,2009 .
[2]孟维军 .地铁车站地下连续墙处理技术研究及其应用[D] .哈尔滨:哈尔滨工程大学,2007 .
[3]秦建兴 .地下连续墙施工过程的质量控制研究[J] .安徽建筑,2012,03:125-126+140 .
[4]周雪莲,余振栋,罗云峰,等 .地下连续墙施工过程中泥浆护壁对槽壁稳定性的影响分析[J] .建筑施工,2014,12:1316-1318 .

相似文献/References:

[1]韩宝祥,吉文佳.浅述泗洪泵站流道层大体积混凝土 施工技术及质量控制[J].江苏水利,2016,(01):23.
 HAN Baoxiang,JI Wenjia.Brief Description on Construction Technique and Quality Control of Mass Concrete for the Sihong Pumping Station Flow Passage[J].JIANGSU WATER RESOURCES,2016,(05):23.
[2]崔彩,杨锋鸽.新沟河延伸拓浚工程江边枢纽船闸闸室施工控制[J].江苏水利,2016,(08):20.
 CUI Cai,YANG Fengge.Construction control of riverside hub lock chamber in Xingouhe extension and dredging project[J].JIANGSU WATER RESOURCES,2016,(05):20.
[3]黎龙凤,张志俊.浅谈梯形(T90)预制混凝土田间渠道的 设计及施工工艺[J].江苏水利,2016,(08):47.
 LI Longfeng,ZHANG Zhijun.Discussion on the design and construction technology of trapezoidal (T90) precast concrete field channel[J].JIANGSU WATER RESOURCES,2016,(05):47.
[4]陈锡林,金忠良,陈于,等.装配式生态护岸工程的设计与施工[J].江苏水利,2022,(06):1.
 CHEN Xilin,JIN Zhongliang,CHEN Yu,et al.Design and Construction of Prefabricated Ecological Revetment Engineering[J].JIANGSU WATER RESOURCES,2022,(05):1.