[1]吴昊天,王振友,宋意勤,等.环太湖西段大堤加固植苇护岸可行性讨论[J].江苏水利,2018,(07):24-28+33.
 WU Haotian,WANG Zhenyou,SONG Yiqin,et al.Discussion on the feasibility of reinforcing reed revetment inw estern section of Taihu Lake[J].JIANGSU WATER RESOURCES,2018,(07):24-28+33.
点击复制

环太湖西段大堤加固植苇护岸可行性讨论()
分享到:

《江苏水利》[ISSN:1006-6977/CN:61-1281/TN]

卷:
期数:
2018年07期
页码:
24-28+33
栏目:
生态与环境
出版日期:
2018-07-17

文章信息/Info

Title:
Discussion on the feasibility of reinforcing reed revetment inw estern section of Taihu Lake
文章编号:
1007-783(9 2018)07-0024-05
作者:
吴昊天1王振友2宋意勤2宋薇薇1
1.江苏省水利勘测设计研究院有限公司,江苏 扬州 225127;2.江苏省工程勘测研究院有限责任公司,江苏 扬州 225002
Author(s):
WU Haotian1WANG Zhenyou2SONG Yiqin2SONG Weiwei1
1. Jiangsu Provincial Water Conservancy Survey and Design Institute Co.,Ltd,Yangzhou 225127,Jiangsu; 2. Jiangsu Engineering Surveying Institute Co. ltd,Yangzhou 225002,Jiangsu
关键词:
风浪特点破坏作用植苇护岸柔化岸线
Keywords:
wind and wave characteristicsdestructive effectreed revetmentflexible coastline
分类号:
TV871
文献标志码:
B
摘要:
太湖属浅水型湖泊,汛期东南风盛行,对西段江苏境内大堤破坏性显著。研究通过太湖风浪特点、风浪对岸坡破坏作用机理分析,认为环太湖西段大堤防洪加固重在防风浪。结合挺水植物芦苇的适应性、消能抗风浪能力,认为环太湖西段大堤加固工程中应用植苇护岸方法进行抗风浪,能够提高抵御流域洪水的能力,并符合太湖治理生态保护、柔化岸线的总体趋势,是可行的加固方案之一。
Abstract:
Taihu Lake is a shallow-water lake. The southeast wind prevail sin flood season, which is destructiv e to the embankment in the western part of Jiangsu. Through then aalysis of the characteristics of wind and waves i n Taihu Lake and the destructive mechanism of wind waves on thea nbk slope, it is considered that the flood protectio n of the embankments in the western part of the Taihu Lake is fuosced on the prevention of wind and waves. Combinin g the adaptability of the reed and the ability to resist wind anwdave of the reed water plant, it is believed that t he application of the reed bank protection method to resist winda vwes in the reinforcement project of the west section of the Taihu Lake can improve the ability to resist the flood ihne triver basin, and conforms to the general trend of t he ecological protection and the softening shoreline in Taihu La,k ewhich is one of the feasible reinforcement schemes .

参考文献/References:

[1]邓越,吴浩云、孙大勇,赵中伟. 环太湖大堤防洪能力浅析[J]. 研究探讨,2015,25(5):72-75.
[2]徐雪红. 太湖流域防洪形势及近期治理防洪标准探讨[J]. 湖泊科学,2000,12(3):199-204.
[3]胡庆华,陈文辽. 苏州太湖避风港工程总体设计[J].水运工程,2009(5):72-76.
[4]陈方,杨旭昌,王玉. 太湖风浪对水环境的影响作用[J].水利发展研究2015,5(12):28-31,34.
[5]邱秀云,阿不都外力,程艳,周著,侯杰. 植物“柔性坝”对水流影响的试验研究[J]. 水力水电技术,2003,34(9):62-65.
[6]才多,诸裕良. 基于弱非线性RIDE 模型的植物消浪数值模拟研究[J].海洋工程,2014,32(6):41-48.
[7]石声汉校注,西北农学院古农学研究室整理,《农政全书校注》[M]. 上册(全三册),上海:上海古籍出版社,1979,346-347.

备注/Memo

备注/Memo:
收稿日期:2018-03-01
作者简介:吴昊天(1990—),男,本科,主要从事水利工程、交通航运工程景观及绿化设计工作。
更新日期/Last Update: 2018-07-15