[1]高 亮,王 强,单体伟,等.新沟河延伸拓浚工程安全管理工作现状分析及对策[J].江苏水利,2020,(增刊2):72-75.
 GAO Liang,WANG Qiang,SHAN Tiwei,et al.Analysis and countermeasures of safety management of Xingou River extension dredging project[J].JIANGSU WATER RESOURCES,2020,(增刊2):72-75.
点击复制

新沟河延伸拓浚工程安全管理工作现状分析及对策()
分享到:

《江苏水利》[ISSN:1006-6977/CN:61-1281/TN]

卷:
期数:
2020年增刊2
页码:
72-75
栏目:
水利工程管理
出版日期:
2021-01-30

文章信息/Info

Title:
Analysis and countermeasures of safety management of Xingou River extension dredging project
文章编号:
1007-7839(2020)S2-0072-04
作者:
高 亮1 王 强1 单体伟2 何书通3
1.常州市新沟河延伸拓浚工程建设处, 江苏 常州 213000; 2.江苏省水利建设工程有限公司, 江苏; 3.江苏省太湖治理工程建设管理局, 江苏 常州 213000
Author(s):
GAO Liang1 WANG Qiang1 SHAN Tiwei2 HE Shutong3
1.Construction Office of Xingou River Extension Dredging Project, Changzhou 213100, China; 2.Jiangsu Hydraulic Engineering Construction Co., Ltd., Yangzhou 225002, China; 3.Jiangsu Province Taihu Governance Project Construction Administration, Changzhou 213000, China
关键词:
安全管理 现状剖析 安全对策
Keywords:
safety management analysis of current situation safety countermeasures
分类号:
TU714
文献标志码:
B
摘要:
工程特点:定位高、工艺复杂和安全管理难度大。重难点:拆除量大、基坑深、交通组织难度大、特种设备和人机数量多,动态管理难,危大工程多等。通过对当前安全现状剖析,存在以下不足:安全管理基础较薄弱、体系不健全、形式大于实效和相关标准、规程的应用不能满足项目要求等。安全对策:引入模板监测系统、枯水季节抢施工、编制拆除专项方案、做好深基坑降排水与监测、成立交通管控领导小组、加强人机管理、做好开工条件审查、实行网格化风险管理、组织综合应急演练等。从根本上遏制或消除重大工伤事故、一般及以上等级事故发生,保证了工程安全有效推进。
Abstract:
Engineering features: high positioning, complex process and difficult safety management. Key and difficult points: large amount of demolition, deep foundation pit, difficult traffic organization, large number of special equipment and man-machine, difficult dynamic management, dangerous and large projects, etc. Through the analysis of the current situation of safety, there were the following shortcomings: weak safety management foundation, unsound system, form greater than actual effect, and the application of relevant standards, regulations couldn't meet the requirements of the project. Safety countermeasures: the introduction of the template monitoring system, rush construction in dry water season, preparation of special plans for dismantling, the establishment of deep foundation pit drainage and monitoring, the establishment of a leading group for traffic control, the strengthening of man-machine management, the inspection of starting conditions, the implementation of grid risk management, the organization of comprehensive emergency drills, etc. The occurrence of major industrial accidents, general and above grade accidents was fundamentally contain or eliminate, which could ensure the safety and effective progress of the project.

参考文献/References:

[1] 刘子系, 边晓阳, 徐嘉, 等. 建设双向泵站形成新型调水引流格局[J]. 江苏水利, 2017(6):54-57, 62.
[2] 夏春梅, 申振森. 桥梁施工监控组织、质量、安全[J]. 科技创新与应用, 2016(35):257.
[3] 孙洪利, 崔永春, 王继华, 魏海. 安全生产网格化监管方法[J]. 劳动保护, 2010(10):70-73.

相似文献/References:

[1]徐佳易,杨 斌,陈新洋.皇晏岭水工隧道工程中安全措施的应用与研究[J].江苏水利,2017,(04):6.
 XU Jiayi,YANG Bin,CHEN Xinyang.Application and research on safety measures in Huangyanling hydraulic tunnel project[J].JIANGSU WATER RESOURCES,2017,(增刊2):6.
[2]蒋一波,范海平,张良群,等.基于BIM+数字孪生技术的水利枢纽工程智慧化安全管理探索[J].江苏水利,2022,(增刊2):18.
 JIANG Yibo,FAN Haiping,ZHANG Liangqun,et al.Exploration of intelligent safety management of water conservancy projects based on BIM + digital twin technology[J].JIANGSU WATER RESOURCES,2022,(增刊2):18.
[3]邵勇,陶飞飞,皮妍玲,等.基于改进LEC法的水利工程安全风险分级评价[J].江苏水利,2023,(06):60.
 SHAO Yong,TAO Feifei,PI Yanling,et al.Study of safety risk grading evaluation of water conservancy project based on improved LEC method[J].JIANGSU WATER RESOURCES,2023,(增刊2):60.

备注/Memo

备注/Memo:
收稿日期:2020-07-06
作者简介:高亮(1977—),男,本科,工程师,主要从事水利工程安全管理工作。
更新日期/Last Update: 2020-12-30