[1]王 豹,龙 俊,李 欣,等.三汊河河口闸工程水平位移成果汇编探析[J].江苏水利,2020,(03):70-72.
 WANG Bao,LONG Jun,LI Xin,et al.Analysis on the results compilation of the horizontal displacement of the Sancha River Estuary Sluice engineering[J].JIANGSU WATER RESOURCES,2020,(03):70-72.
点击复制

三汊河河口闸工程水平位移成果汇编探析()
分享到:

《江苏水利》[ISSN:1006-6977/CN:61-1281/TN]

卷:
期数:
2020年03期
页码:
70-72
栏目:
水利工程管理
出版日期:
2020-04-27

文章信息/Info

Title:
Analysis on the results compilation of the horizontal displacement of the Sancha River Estuary Sluice engineering
文章编号:
1007-7839(2020)03-0070-03
作者:
王 豹1 龙 俊1 李 欣1 温少林2
1.江苏省洪泽湖水利工程管理处, 江苏 淮安 223100; 2.南京市三汊河河口闸管理处, 江苏 南京 210036
Author(s):
WANG Bao LONG Jun LI Xin WEN Shaolin
1.The Hongze Lake Water Conservancy Project Management Office of Jiangsu Province, Huai'an 223100, Jiangsu; 2.Nanjing Sancha River Estuary Gate Administration, Nanjing 210036, Jiangsu
关键词:
三汊河河口闸 工程观测 水平位移 方向转换
Keywords:
Sancha River Estuary Sluice engineering observation horizontal displacement direction of transformation
分类号:
TV663
文献标志码:
B
摘要:
三汊河河口闸工程每年汛前、汛后均进行闸身水平位移观测,观测结束后按照规程要求对成果进行整理并对比分析数据状况,一直采用的是经线方向与纬线方向2组数值进行分析,成果虽然具备一定的参考性,但是与工程现场直接关联性较差。而将数值予以转换,投影至顺应水流方向和垂直水流方向进行对比,更利于将分析结果与工程实际相结合,便于直观地观察工程位移情况。
Abstract:
The horizontal displacement of the sluice body of the Sanyahe Estuary Sluice Project was observed before and after the flood every year. The results were sorted out, compared and analyzed according to the requirements of the procedure after the observation. Two sets of values of longitude direction and latitude direction had been used for the analysis. The results had a certain reference value, but less direct relevance and engineering site. However, the numerical value was converted and projected to the flow direction and the vertical flow direction for comparison and analysis, which was more conducive to the combination of the analysis results and the actual engineering, so as to intuitively observe the displacement of the project.

参考文献/References:

[1] 温少林, 傅金, 王豹. 浅谈远程控制系统在三汊河河口闸运行管理中的运用[J]. 水利建设与管理, 2018(3):12-18.
[2] 江苏省水利厅工程管理处, 江苏省河道管理局DB32/T 1713-2011江苏省水利工程观测规程[S]. 南京:江苏省质量技术监督局, 2011:12-15.
[3] 钟勇, 吕梅, 朱耀. 汉江王甫洲水利枢纽泄水闸水平位移监测[J]. 甘肃水利水电技术, 2010(2):19-20.
[4] 秦涛, 岳涛, 滕锐. 引黄水闸沉陷位移、水平位移观测方法刍议[J]. 科技信息, 2011(27):817-818.

相似文献/References:

[1]严 励.淮安二堡船闸工程观测方法的设计与应用[J].江苏水利,2021,(02):63.
 YAN Li.Design and application of observation method for Huaian Erbao Lock Engineering[J].JIANGSU WATER RESOURCES,2021,(03):63.
[2]王 俊,缪融融,翁松干.新沂河海口控制工程垂直位移变化研究[J].江苏水利,2021,(10):43.
 WANG Jun,MIAO Rongrong,WENG Songgan.Study on vertical displacement change of Xinyi river estuary control project[J].JIANGSU WATER RESOURCES,2021,(03):43.

备注/Memo

备注/Memo:
收稿日期:2019-08-14
作者简介:王豹(1989-),男,工程师,主要从事水利工程生产运行管理工作。E-mail:786494269@qq.com
更新日期/Last Update: 2020-03-20